FAT / SAT Acceptance Sign-off

Acceptance Register · Punch List · Sign-off Gate · Hand-over

0/4 steps · 0%

Curated study · fixed values

Mission Brief

The Signature That Energizes a Station

Every test is run, every report filed. What remains is the decision: is this station fit to hand over? The Factory Acceptance Test proved the panels in the shop; the Site Acceptance Test proved them energized in the field. Now the whole campaign rolls up into one acceptance register — every discipline, every item — and one gate decides it: no open critical or major defect, nothing left pending. Cross that gate and the station is yours to run; miss it and the punch list comes first.

  • Compile the acceptance register across every discipline
  • Classify each item — pass, punch (with severity), pending, or N/A
  • Apply the sign-off gate: no open critical/major, nothing pending
  • Carry minor defects as a punch list under conditional acceptance
  • Issue the acceptance certificate for hand-over